Final Inspections & Trials : Hydraulic System : Additional works T56 + Amendment works T57 in order to finish and close jobs.

Final Inspections & Trials : Hydraulic System : Additional works T56 + T57

Work done for T56 additional and T57 amendment works :-

1) Approached to Mae Taeng in order to solve the problem with our staffs who have worked over 3 months on T56+T57 worksite.

2) To make a trial , Pressure Trial & Testing at T56 :- CREEPERS & ERECTORS Hydraulic system Testing & Trials , Super High Pressure Power Unit at Max. Working Pressure 400 bar trial.

3) To Inspect on the Assembly hydraulic hose workshop for T57 amendment works.

Finished our final inspection & trial job.